IRONG Offshore Wellhead Facilities

Client: Vestigo Petroleum Sdn Bhd

Field: IRONG

Facilities: Wellhead Platform 

Location: Malaysia

Synergy's Scope of Work 

Synergy was requested to undertake development of IRONG  field that consists of satellite wellhead platforms, rigid pipeline for full well stream from IRONG WHP to a Pipeline End Termination (PLET) and a flexible flow line for full well stream from PLET to BERANTAI FPSO. 

Vestigo/MMHE  requested Synergy to design an unmanned minimal facilities wellhead platform at the Irong Field. Synergy performed the detail engineering design for the whole topside facilities of the wellhead platform with a topside weight 350 tonnes.

Key Project Achievements 

1. Completed FEED and Detail Engineering (AFC) within 4 months.